Issue regarding power curtailment
#1
Hi, I implemented power curtailment following the EU-TIMES approach using the provided files. However, the simulation results indicate that there is no recorded activity for renewable energy (RE) production (e.g., missing ACT values). Additionally, the output only includes NCapM and ActM, without the expected renewable energy real consumption and curtailment data.
How can we resolve this issue and ensure that RE production is properly reflected in the model results?

Best,
Xiao


Attached Files
.xlsx   SubRES_14_TECHS_STORAGE.xlsx (Size: 881.43 KB / Downloads: 3)
.xlsx   Scen_Storage_NCAPAFC.xlsx (Size: 34.91 KB / Downloads: 4)
Reply
#2
How did you conclude that there is no RE production?
[+] 1 user Likes AKanudia's post
Reply
#3
Hi Amit,

Sorry for the late reply. It has been solved, many thanks!

Best,
Xiao
Reply


Possibly Related Threads…
Thread Author Replies Views Last Post
  Issue inserting small values for RCAP_BND till 12 758 10-03-2025, 10:12 AM
Last Post: Ravinder
  Issue with UC on cum subsidies for period of years janis 17 2,647 24-02-2025, 10:03 PM
Last Post: janis
  Power output constraint - EV battery Kristina.Haaskjold 5 622 23-01-2025, 07:19 PM
Last Post: Kristina.Haaskjold
  Issue with Elastic Demand Hesam 10 1,251 04-10-2024, 03:15 PM
Last Post: Ravinder
  About the power curtailment and output shortage [email protected] 0 285 25-08-2024, 01:12 AM
Last Post: [email protected]
  Issue with Sync Log report LucasD 1 563 14-08-2024, 03:43 PM
Last Post: Ravinder
  Issue in Demand Modelling for a specific sector and its results namrata9815 2 674 16-07-2024, 01:04 PM
Last Post: namrata9815
  VRE curtailment seanli12354 0 326 23-06-2024, 07:09 AM
Last Post: seanli12354
  The power storage [email protected] 0 567 15-05-2024, 11:30 PM
Last Post: [email protected]
  New stock of power plants / new installed capacity Sol 2 996 24-01-2024, 02:42 PM
Last Post: Antti-L

Forum Jump:


Users browsing this thread: 1 Guest(s)