18-01-2011, 10:20 AM
Hello,
I tried to set up a simple model, but encountered problems with the definition of the capital cost. Whenever I use NCAP_COST (or INVCOST) to define the total cost of investment in a new capacity,
GAMS reports an "Unexpected Termination of Run!" GAMS runs properly, if I do not use this definition, but a Dummy Import is used to calculate the prices. What am I doing wrong? I'll post my process. Hopefully, someone can help. Thanks a lot in advance!
seb
I tried to set up a simple model, but encountered problems with the definition of the capital cost. Whenever I use NCAP_COST (or INVCOST) to define the total cost of investment in a new capacity,
GAMS reports an "Unexpected Termination of Run!" GAMS runs properly, if I do not use this definition, but a Dummy Import is used to calculate the prices. What am I doing wrong? I'll post my process. Hopefully, someone can help. Thanks a lot in advance!
seb
~FI_T | |||||||||||||||||||||
TechName | *TechDesc | Comm-IN | Comm-OUT | CUM | COST | EFF | CEFF-I | STG_EFF | STG_LOSS | Stock | AFA | NCAP_COST | FIXOM | VAROM | Life | CAP2ACT | START | Share-I | CEH | CHPR | BNDACT |
*Technology Name | Technology Description | Input Commodity | Output Commodity | Reserves Cumulative Value | Extraction cost or Import Price or Export Price | Efficiency | Commodity Input Efficiency | Existing Installed Capacity | Annual Availability Factor | Total cost of investment in new capacity | Fixed O&M Cost | Variable O&M Cost | Lifetime of Process | Capacity to Activity Factor | Input Share | Ratio of electricity lost to output gained | Output to Power Ratio | Extraction Bound, Renewable Availability Bound, Import/Export Bound and Process Output Bound | |||
EHCO00 | Coal plant | HCO | ELC | 33% | 5 | 5 | 1 | 2010 | |||||||||||||
EHYD00 | Hydro plant | HYD | ELC | 80% | 120 | 10 | 1 | 2222 | |||||||||||||
ENGA | Gas plant | NGA | ELC | 50% | 0.5 | 2 | 1 | 2222 | |||||||||||||
ESOLPV | Solar PV | SOL | ELC | 100% | 80 | 5 | 1 | 2222 | |||||||||||||
EPUMP | Pumped hydro | ELC | ELC | 100% | 60% | 10 | 5 | 1 | |||||||||||||
MINHCO | Coal mine | HCO | 4 | ||||||||||||||||||
MINNGA | Mining gas | NGA | 6 | ||||||||||||||||||
RNWHYD | Hydro dam | HYD | 0.5 | ||||||||||||||||||
RNWSOL | Solar | SOL | 0 |