Veda2.0 Released!


CO2 BOUND will influence values in base year
#1
Dear all,
    I have tested my model and DemoS_012, and I found a bound on CO2 emission would influence values in base year. For example, if CO2 emission in base year (2012) is 1000, and it will decrease to 800 with the UP CO2 BOUND in 2020 other than in 2012. In my opinion, outward constraints should not influence values in base year, and I found values in base seemed to be unchanged in many published papers. I really need your help. Thank you for any reply!
Reply
#2
AFA~FX seems to be the reason, but I need AFA~FX to make electricity generation developing as I surposed. Is there any method to solve it?
Reply
#3
About your first post you are right, generally this constraint should not influence base year results. I had a look at DemoS_012 and base year emissions are always the same in any scenario.

In your case other constraints and/or input are forcing the model to reduce emissions already in the base year. You are suggesting AFA~FX but I don't have enough information about your model to help.

How many technologies are using AFA~FX?

If you need/want fix electricity production from some technologies I suggest to use ACT_BND~FX and not AFA~FX. You could specify ACT_BND~FX some some periods and then relax the model removing this FX bound. 

For your information ETSAP is organize at least two times per year TIMES training courses in different countries. You can find information on the ETSAP web site.

Reply
#4
Thank you for you reply!
Reply


Possibly Related Threads…
Thread Author Replies Views Last Post
  trade bound [email protected] 2 407 18-04-2025, 05:50 AM
Last Post: [email protected]
  Early retirement for each year Sandro_Luh 17 9,243 02-10-2023, 05:08 PM
Last Post: vincedh
  About base year process and New tech guozhi1305 0 1,057 21-05-2022, 04:53 PM
Last Post: guozhi1305
  LCOE values xavier 2 3,052 09-08-2021, 11:39 PM
Last Post: xavier
Photo VAR_CUMFLO upper bound divided by 10 canismajoris 7 8,347 07-05-2021, 05:55 PM
Last Post: DOlih
  Activating NT-PWR not in use in base year xavier 4 4,842 22-02-2021, 11:04 PM
Last Post: xavier
  How to set emission factor for each year of a specific process during its lifetime? Xin Wang 14 22,371 06-01-2021, 11:17 PM
Last Post: Antti-L
  A very high value electricity price in base year Antti-L 0 2,250 29-05-2020, 01:25 AM
Last Post: Antti-L
  Base year setting guozhi1305 0 2,555 06-06-2019, 12:23 PM
Last Post: guozhi1305
  Bound infeasibility Tanzeel 1 3,656 03-06-2019, 11:33 PM
Last Post: Tanzeel

Forum Jump:


Users browsing this thread: 1 Guest(s)