30-10-2017, 05:53 PM
Hi,
I am modeling HEPPs in the base scenario and I saw deviation between the total production of all HEPPs and the given balance table.
After checking all reports related to balance table, I realized that this deviation comes from the calculation of Total Production.
For instance, we have a HEPP with the installed capacity of 2.405 GW. Considering the AFA of 0.86 and CAP2ACT (PJ/GW) 31.536, we reach to 2.405*0.86*31.536 = 65 PJ as the total production. However, this dam is producing 32 PJ based on documents. How can we explain these differences?
Thanks again
I am modeling HEPPs in the base scenario and I saw deviation between the total production of all HEPPs and the given balance table.
After checking all reports related to balance table, I realized that this deviation comes from the calculation of Total Production.
For instance, we have a HEPP with the installed capacity of 2.405 GW. Considering the AFA of 0.86 and CAP2ACT (PJ/GW) 31.536, we reach to 2.405*0.86*31.536 = 65 PJ as the total production. However, this dam is producing 32 PJ based on documents. How can we explain these differences?
Thanks again