Veda2.0 Released!


Capacity Factor
#1
Hi,

I need to set an upper bound on capacity for wind power plant and I have max capacity factor of the power plant from 2015 to 2025 (32%,32.6%, and 33.1%). How can I set user constraint for the capacity factor of the power plant? I don't have the max capacity of the power plant I only have capacity factor. So I did as below, but I know something has missed...
   
UC_N                       Pset_Set  Pset_PN     Pset_CI  Pset_CO    Year  LimType  UC_CAP   UC_RHSRT UC_MaxWindCL4CAP   ELE         EWNDCL4    WND        ELC          2015     UP       -0.32            0                                                    ELE        EWNDCL4     WND        ELC         2020     UP      -0.326            0                                                 ELE         EWNDCL4     WND        ELC         2025     UP     -0.331          0                    

Thanks for your help,
Samaneh                    
Reply
#2
Sorry I think I need to rewrite the constraint.

Pset_Set  Pset_PN     Pset_CI  Pset_CO    Year  LimType  UC_CAP   UC_RHSRT
ELE         EWNDCL4    WND        ELC          2015     UP       -0.32            0
ELE        EWNDCL4     WND        ELC         2020     UP      -0.326            0
ELE         EWNDCL4     WND        ELC         2025     UP     -0.331          0                    

Should this table be ~UC_T or ~UC_T:UC_RHSRT?
Thanks,
Samaneh
Reply
#3
What are you trying to add over what the attribute AF would do?

In general, one should write the equation that needs to be expressed as a UC. Please do an exercise for me: translate the UC above into an equation.

Constructing UCs will be very frustrating (and risky) unless the underlying equations are completely clear to the user.
Reply
#4
I already had AF in my model, but I solved my problem with applying constraint on the amount of wind capacity.

Thanks,
Samaneh
Reply
#5
Good that you got things to work.
However, if you are dealing with only one wind technology then CAP_BND should be enough.
Reply


Possibly Related Threads…
Thread Author Replies Views Last Post
  how to define the capacity or stock for storage? guozhi1305 6 2,350 08-05-2024, 05:47 PM
Last Post: guozhi1305
  About RNW capacity guozhi1305 4 3,078 19-05-2022, 08:13 AM
Last Post: guozhi1305
  How to set emission factor for each year of a specific process during its lifetime? Xin Wang 14 21,884 06-01-2021, 11:17 PM
Last Post: Antti-L
  Solar lower costs impact capacity constraints LucasD 10 9,591 18-12-2020, 03:04 PM
Last Post: AKanudia
  Storage output without capacity deployment ach 3 4,777 15-05-2020, 03:04 PM
Last Post: Antti-L
  Too much installed capacity required Juliana_Barbosa 1 4,383 16-09-2018, 06:35 PM
Last Post: Antti-L
  UC Capacity Growth Constraint - Troubles at end of horizon Giulia Realmonte 20 35,830 19-04-2018, 02:13 PM
Last Post: Giulia Realmonte
  Assessing diesel imports due to sulfur standard emission factor anadeveza 1 4,514 23-12-2017, 01:19 AM
Last Post: Antti-L
Question Lower capacity, higher demand -> Still demand is met Simon Andersen 6 11,237 12-12-2017, 01:58 AM
Last Post: Simon Andersen
  Calculating total production based on capacity in Hydroelectric power plants (HEPPs) danialesm 2 5,966 30-10-2017, 06:52 PM
Last Post: danialesm

Forum Jump:


Users browsing this thread: 1 Guest(s)