Veda2.0 Released!


partial run
#1
Dear All,

I would like to ask a (probably) simple, general question:

We are building a national energy model, based on the Starter platform. Since we are quite new with TIMES-VEDA model and we are modelling several sectors (e.g. transportation, power, industry) simultaneously, I was wondering if it is possible to run the model partially: considering one sector at once? (for both calibration and "model learning" purposes)


If it is so, could you please help, how should one proceed on this? Is it enough to import into the VEDA-FE only those excels which are relevant for the given sector?


Thank you very much for your help in advance.

Best regards,
Viktor
Reply
#2
Hi Viktor,

Sorry for the long delay in getting back to you --- I've been unavailable for a bit.

Yes, simply set the demand project (COM_PROJ in the DEM template) = 0 for the sectors you're not ready to run.

Regards,
Gary
g2
Reply