Veda2.0 Released!


IMPNGZ Dummy Issue
#1
I am modelling an Indian power system for 2047.

I am facing a problem---Even though there is sufficient coal, gas and biomass capacity available yet the model uses IMPNRGZ along with only those technologies having 'zero' variable cost.

My model has 12 months as seasons and each season has a representative day i.e.total 12*24=288 tslv. PRC_CAPACT=31.536

Kindly help me in this regard.
Reply
#2
> Even though there is sufficient coal, gas and biomass capacity available yet the model uses IMPNRGZ along with only those technologies having 'zero' variable cost.

If there is sufficient coal, gas and biomass capacity available, you can disable the dummy import processes:
   

Then the model will no longer be spuriously using IMPNRGZ.  Wink
Reply


Possibly Related Threads…
Thread Author Replies Views Last Post
  Dummy import Emisssions Saad Awan 2 1,416 03-07-2023, 11:30 AM
Last Post: Saad Awan
  VFE case export issue james 1 2,379 04-06-2021, 07:44 AM
Last Post: AKanudia
  Issue after Windows-Office update Luc 7 8,932 11-11-2020, 08:39 AM
Last Post: guozhi1305
Photo SOLVE ISSUE JozefO 10 12,269 08-10-2020, 12:30 AM
Last Post: JozefO
  impact of YRFR on dummy imports svecjos 3 4,861 20-07-2020, 11:12 PM
Last Post: svecjos
  Issue with constraint: Error Code 172 NeilGrant 5 7,415 28-05-2020, 02:08 PM
Last Post: NeilGrant
  Issue with EQ_Combal and VAR_Comnet NeilGrant 6 8,952 15-11-2019, 08:18 PM
Last Post: Antti-L
  Issue when running TIAM with Price-Elastic Demand NeilGrant 2 5,142 09-08-2019, 03:44 PM
Last Post: NeilGrant
  QA Log error/process PCG issue ach 1 4,168 31-12-2018, 06:51 PM
Last Post: Antti-L
  Infeasibility related to Import Dummy Process Raulm 0 3,779 09-12-2016, 10:11 PM
Last Post: Raulm

Forum Jump:


Users browsing this thread: 1 Guest(s)