29-09-2021, 12:42 PM
(28-09-2021, 07:11 PM)Antti-L Wrote: Maybe you did not notice from that thread that the "fix investment idea" was never considered.
Instead, the facility for fixing new capacities to a previous solution was implemented already in TIMES v4.4.2, over a year ago. So, that can indeed be used, and I don't see why it couldn't be used regardless of the timeslice configuration. But it is only related to capacities and not investment costs, which may thus be different.
Thanks Antti.